Question 1.1.Which of the following statements about project crashing is false?(Points : 3)
The overall project time is reduced by crashing activities on one or more critical paths.
It is best to crash an activity with the cheapest cost to crash per week.
As activities are crashed in a project network, it is possible for more than one path to be critical.
In order to reduce the overall project time, it may be necessary to crash more than one activity.
Project crashing problems can be solved using linear programming.
Question 2.2.Considering the following Activity-On-Node (AON) project (activity completion times are in days),what is the critical path?
Activity-On-Node
Click hereto view a Word version of the project.(Points : 3)
ABEF
ACEF
ACDF
ABDF
Question 3.3.Considering the following Activity-On-Node (AON) project (activity completion times are in days),what is the slack time associated with activity E?
Activity-On-Node
Click hereto view a Word version of the project.(Points : 3)
0 days
1 day
2 days
3 days
Question 4.4.Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity’s completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively.What is the standard deviation associated with the completion time of activity B?
Activity-On-Node-2
Click hereto view a Word version of the project.(Points : 3)
0.0245 days
0.6667 days
0.3145 days
0.3333 days
Question 5.5.Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity’s completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively.What is the expected completion time of the critical path?
Activity-On-Node-2
Click hereto view a Word version of the project.(Points : 3)
14 days
19 days
20 days
23 days
Question 6.6.Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B A
C A
D B, C
E B, C
F D, E
G F
Jamie was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 4
B 4
C 5
D 3
E 3
F 2
G 1
Considering the information above, what is the slack for activities E and F respectively?(Points : 3)
0 days; 0 days
0 days; 1 day
1 day; 0 days
1 day; 1 day
Question 7.7.Consider the following set of activities that must be completed in order to prep a new home for painting:
Immediate
Activity Predecessors
A –
B –
C A, B
D C
E C
F D, E
G E
H F, G
Also assume that the painters were able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2
Considering the information above, what is the earliest finish time for activity F?(Points : 3)
10 days
12 days
14 days
16 days
Question 8.8.Consider the following set of activities that must be completed in order to prep a new home for painting:
Immediate
Activity Predecessors
A –
B –
C A, B
D C
E C
F D, E
G E
H F, G
Also assume that the painters were able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2
Considering the information above, what is the critical path?(Points : 3)
ACDFH
ACEFH
BCDFH
BCEGH
Question 9.9.Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B –
C –
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the length of the project?(Points : 3)
14 days
15 days
17 days
19 days
Question 10.10.Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B –
C –
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the critical path?(Points : 3)
CEGHJ
ADFIJ
CEFIJ
ADFHJ
Why Choose Us
Quality Papers
We value our clients. For this reason, we ensure that each paper is written carefully as per the instructions provided by the client. Our editing team also checks all the papers to ensure that they have been completed as per the expectations.
Professional Academic Writers
Over the years, our Acme Homework has managed to secure the most qualified, reliable and experienced team of writers. The company has also ensured continued training and development of the team members to ensure that it keep up with the rising Academic Trends.
Affordable Prices
Our prices are fairly priced in such a way that ensures affordability. Additionally, you can get a free price quotation by clicking on the "Place Order" button.
On-Time delivery
We pay strict attention on deadlines. For this reason, we ensure that all papers are submitted earlier, even before the deadline indicated by the customer. For this reason, the client can go through the work and review everything.
100% Originality
At Essay USA, all papers are plagiarism-free as they are written from scratch. We have taken strict measures to ensure that there is no similarity on all papers and that citations are included as per the standards set.
Customer Support 24/7
Our support team is readily available to provide any guidance/help on our platform at any time of the day/night. Feel free to contact us via the Chat window or support email: support@acmehomework.com.
Try it now!
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
Essay USA has stood as the world’s leading custom essay writing services providers. Once you enter all the details in the order form under the place order button, the rest is up to us.
Essays
At Essay USA, we prioritize on all aspects that bring about a good grade such as impeccable grammar, proper structure, zero-plagiarism and conformance to guidelines. Our experienced team of writers will help you completed your essays and other assignments.
Admissions
Admission and Business Papers
Be assured that you’ll definitely get accepted to the Master’s level program at any university once you enter all the details in the order form. We won’t leave you here; we will also help you secure a good position in your aspired workplace by creating an outstanding resume or portfolio once you place an order.
Editing
Editing and Proofreading
Our skilled editing and writing team will help you restructure you paper, paraphrase, correct grammar and replace plagiarized sections on your paper just on time. The service is geared toward eliminating any mistakes and rather enhancing better quality.
Coursework
Technical papers
We have writers in almost all fields including the most technical fields. You don’t have to worry about the complexity of your paper. Simply enter as much details as possible in the place order section.