Scheduling Resources and Costs
Project Management Ch 8
6th Edition
Your Results:
The answer for each question is indicated by a .
1
Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource
A)
Shifting
B)
Effectiveness
C)
Manipulating
D)
Smoothing
E)
Allocation
2
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
A)
Activity delays
B)
Project delays
C)
Difficulty in taking quick ive action
D)
Increase costs
E)
Scope creep
3
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.
A)
Physical
B)
Technical
C)
Resource
D)
Schedule
E)
Time
4
Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?
A)
Physical
B)
Technical
C)
People
D)
Equipment
E)
Time
5
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.
A)
Time, quality
B)
Quality, resource
C)
Cost, time
D)
Quality, cost
E)
Time, resource
6
In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as __________ constrained.
A)
Time
B)
Quality
C)
Cost
D)
Performance
E)
Resource
7
Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?
A)
Resources have been assigned to each activity so they are adequate to complete the project on time
B)
Activity 4 cannot be completed before activity 1
C)
The project completion date can be established
D)
The project is ready to be implemented
E)
All of these are true statements once technical constraints have been established
8
Resource leveling or smoothing can have all the following results on a project EXCEPT
A)
Lower peak resource demand
B)
Reduced resource need over the life of the project
C)
Reduced fluctuations in resource demand
D)
A longer project duration
E)
A more sensitive network
9
In a resource-constrained project, which of the following is most likely to be changed?
A)
The completion date
B)
The budget
C)
Project quality
D)
Resource levels
E)
Scope creep
10
In a resource-constrained project the second priority in assigning resources is usually given to activities with the
A)
Smallest duration
B)
Least slack
C)
Most slack
D)
Lowest identification number
E)
Highest cost
11
Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first?
A)
The activity with the smallest duration
B)
The activity with the least slack
C)
The activity with the most slack
D)
The activity with the lowest identification number
E)
The activity with the highest cost
12
Splitting an activity can result in all of the following EXCEPT
A)
Less people needed to work on an activity
B)
Possible startup and shutdown costs
C)
A resource may being moved from one activity to another and then back again
D)
Activity work being placed on hold for a period of time until more resources are available
E)
A better project schedule
13
All of the following are benefits of scheduling resources before project implementation EXCEPT:
A)
It allows time for considering reasonable options if resource constraints do exist
B)
The project completion date can be established
C)
Work packages can be time-phased
D)
It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E)
It ensures low network sensitivity
14
These are all guidelines a project manager should consider when assigning project work EXCEPT
A)
Select people with compatible work habits and personalities
B)
Always assign the best people to the most difficult tasks
C)
When possible, team veterans up with new hires
D)
Select individuals with skillsets that complement each other
E)
Have people work together early so that they can become familiar with each other
15
Why is it necessary to have a time-phased budget baseline?
A)
It is needed for proper resource allocation
B)
It is needed in order to know how much work was accomplished for the money spent
C)
It is needed to reduce schedule slippage when scheduling multi-project resources
D)
It is not necessary to have a time-phased budget baseline
E)
It is needed to reduce fluctuations in cash flow during the project
Why Choose Us
Quality Papers
We value our clients. For this reason, we ensure that each paper is written carefully as per the instructions provided by the client. Our editing team also checks all the papers to ensure that they have been completed as per the expectations.
Professional Academic Writers
Over the years, our Acme Homework has managed to secure the most qualified, reliable and experienced team of writers. The company has also ensured continued training and development of the team members to ensure that it keep up with the rising Academic Trends.
Affordable Prices
Our prices are fairly priced in such a way that ensures affordability. Additionally, you can get a free price quotation by clicking on the "Place Order" button.
On-Time delivery
We pay strict attention on deadlines. For this reason, we ensure that all papers are submitted earlier, even before the deadline indicated by the customer. For this reason, the client can go through the work and review everything.
100% Originality
At Essay USA, all papers are plagiarism-free as they are written from scratch. We have taken strict measures to ensure that there is no similarity on all papers and that citations are included as per the standards set.
Customer Support 24/7
Our support team is readily available to provide any guidance/help on our platform at any time of the day/night. Feel free to contact us via the Chat window or support email: support@acmehomework.com.
Try it now!
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
Essay USA has stood as the world’s leading custom essay writing services providers. Once you enter all the details in the order form under the place order button, the rest is up to us.
Essays
At Essay USA, we prioritize on all aspects that bring about a good grade such as impeccable grammar, proper structure, zero-plagiarism and conformance to guidelines. Our experienced team of writers will help you completed your essays and other assignments.
Admissions
Admission and Business Papers
Be assured that you’ll definitely get accepted to the Master’s level program at any university once you enter all the details in the order form. We won’t leave you here; we will also help you secure a good position in your aspired workplace by creating an outstanding resume or portfolio once you place an order.
Editing
Editing and Proofreading
Our skilled editing and writing team will help you restructure you paper, paraphrase, correct grammar and replace plagiarized sections on your paper just on time. The service is geared toward eliminating any mistakes and rather enhancing better quality.
Coursework
Technical papers
We have writers in almost all fields including the most technical fields. You don’t have to worry about the complexity of your paper. Simply enter as much details as possible in the place order section.